Plaza of the Rockies
|
Nor’wood Development hired Cobb Mechanical to work directly with Y.O.W. Architects and GE Johnson, general contractor, on the Plaza of the Rockies project. This consisted of a south tower 13-story office building with parking garage, totaling 375,000 square feet. The mechanical portion of the project included a central built-up air handling system, three 100HP vane axial supply fans, three return air fans, 100% outside air economizer, two 300 ton water-cooled chillers, two cell-cooling towers, a flat-plate heat exchanger and supply/exhaust fan sequencing for a complete smoke control system. There were waste/vent and dome4stic water plumbing systems for public restrooms on each floor. |
back |